Kinyinya Building Progess

Our main aim for 2024 is to complete the building of a new dormitory with toilets for the girls, and make progress towards fencing the school grounds.

Recent work has seen the windows and doors inserted and the internal plastering completed.

Achieved to date at Kinyinya

  1. One complete Accommodation hall for deaf girls and boys (2003-2005)
  2. Two Classroom blocks (2004)
  3. Installation of two large water tanks (2006)
  4. Five complete Classroom blocks and an office (2008)
  5. Two Units of teachers House (2008)
  6. Dining Hall and kitchen (2012)
  7. Vocation Learning centre (2014)
  8. Connection to electricity supply and supply of computer (2016)
  9. Supply of motorbike to help school governors travel to raise funds (2017)
  10. Start foundation work for new girls dormitory (2018)
  11. Complete foundation and walls of the new dormitory (2019-20)
  12. Successfully dug a well for water (2020)
  13. A second well needed to be dug as the first failed to supply enough water (2021)
  14. New water tank installed with an electric pump to get water up the hill to the tank (2023)
  15. Completion of roofing and plastering of the new dormitory. (2023)
  16. Supply of knitting machines, two computers, a router and phone contract to connect to the Internet (2023)

Foundation slab completed

Foundation work at different stages